Remote Solar Hybrid with Parallel Inverters and Remote Monitoring
The Nagoya 200kW BESS project in Japan adds a BESS system to an existing 1 MW built on a reclaimed industrail site. The Project provides another 250kW of solar PV and ESS to enable load shifting and peak demand management. The Energy system is charged by solar each day and at a preset time.say 4 PM the ESS exports a set 150kW of power into the grid. This continues each day until the day reaches a low cahrge level.
Total diesel generation is 600kW and total solar and wind is 800kW. In order to maximize the penetration the total battery is 8 MWh of lead acid batteries.